Project: 5947 CTL Landfill Gas Project - Request for post-registration changes
Project 5947 CTL Landfill Gas Project
PRC ref PRC-5947-002
Process track Issuance
DOE RINA
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
No changes
Methodology(ies) list
Standardized baseline(s) list
DOE conducted validation of the changes When performing a verification for the project activity or PoA stated above (See footnote 1 below)
Type of submission Temporary deviations from the monitoring plan or the monitoring methodology
  • Applicable period for proposed deviations (inclusive): 15 Sep 2014 - 27 Apr 2017

Corrections that do not affect project design
  • All changes are in Appendix 1 of the CDM project standard? Yes
Applicable crediting period 01 Apr 13 - 31 Mar 20
Assessment opinion Assessment opinion (390 KB)
Revised PDD Revised PDD (2903 KB)   Revised PDD - track changes (2947 KB)
Supplementary documents Appendix 1 - EcoUrbis PRC CER Spreadsheet_corrected_v7 2017 11 13 JAS.xls (602 KB)
Signed form Signed form (202 KB)
DOE clarification
VVS version VVS 9.0
Current status 29 Jan 18 - Approved
Effective approval date: 29 Jan 18
Historic statuses 29 Dec 17 - Request published