09:55 10 Jan 25
Project:
2876 Lahendong II-20 MW Geothermal Project
- Request for post-registration changes
Project | 2876 Lahendong II-20 MW Geothermal Project |
---|---|
PRC ref | PRC-2876-002 |
Process track | Issuance |
DOE | AENOR |
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes |
|
Methodology(ies) list | |
Standardized baseline(s) list | |
DOE conducted validation of the changes | When performing a verification for the project activity or PoA stated above (See footnote 1 below) |
Type of submission |
Temporary deviations from the monitoring plan or the monitoring methodology
|
Assessment opinion | Assessment opinion (311 KB) |
Revised PDD | |
Supplementary documents |
Appendix 1 - CDM Lhd2 - Emission reductions 2ª verification.xls (1809 KB)
|
Signed form | Signed form (436 KB) |
DOE clarification | |
VVS version | VVS 2.0 |
Current status | 14 Mar 14 -
Approved
Effective approval date: 14 Mar 14
|
Historic statuses |
13 Feb 14 -
Request published |
Offset now: visit the United Nations Carbon Offset Platform