04:23 27 Dec 24
Project:
1424 Carhuaquero IV Hydroelectric Power Plant
- Request for post-registration changes
Project | 1424 Carhuaquero IV Hydroelectric Power Plant |
---|---|
PRC ref | PRC-1424-001 |
Process track | Prior approval |
DOE | AENOR |
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes |
|
Methodology(ies) list | |
Standardized baseline(s) list | |
DOE conducted validation of the changes | When performing a verification for the project activity or PoA stated above (See footnote 1 below) |
Type of submission |
Temporary deviations from the monitoring plan or the monitoring methodology
Corrections that do not affect project design
Permanent changes from the monitoring plan or the monitoring methodology
Changes to the project or programme design
|
Applicable crediting period | 03 May 08 - 02 May 15 |
Assessment opinion | Assessment opinion (712 KB) |
Revised PDD | Revised PDD (1810 KB) Revised PDD - track changes (3005 KB) |
Supplementary documents |
Appendix 1 - Carhuaquero IV EGh 1 Jan 2009 - 31 Dec 2009 deviation.zip (5565 KB)
Appendix 2 - Carhuaquero IV EGh 1 Jan 2010 - 31 Dec 2010deviation.zip (5694 KB) Appendix 3 - Carhuaquero IV EGh 1 Jan 2011 - 31 Dec 2011deviation.zip (5642 KB) Appendix 4 - DQA Report P13-0142#1 ed.0 ENGLISH.pdf (193 KB) |
Signed form | Signed form (1367 KB) |
DOE clarification | |
VVS version | VVS 2.0 |
Current status | 04 Apr 14 -
Approved
Effective approval date: 04 Apr 14
|
Historic statuses |
04 Mar 14 -
Published 04 Mar 14 - Summary note being prepared 14 Mar 14 - Awaiting EB decision |
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: