08:17 10 Feb 25
Project:
4217 Bujagali Hydropower Project
- Request for post-registration changes
Project | 4217 Bujagali Hydropower Project |
---|---|
PRC ref | PRC-4217-002 |
Process track | Issuance |
DOE | AENOR |
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes |
No changes |
Methodology(ies) list | |
Standardized baseline(s) list | |
DOE conducted validation of the changes | When performing a verification for the project activity or PoA stated above (See footnote 1 below) |
Type of submission |
Corrections that do not affect project design
|
Applicable crediting period | 01 Dec 11 - 30 Nov 18 |
Assessment opinion |
![]() |
Revised PDD |
![]() ![]() |
Supplementary documents | |
Signed form |
![]() |
DOE clarification | |
VVS version | VVS 2.0 |
Current status | 31 May 18 -
Approved
Effective approval date: 31 May 18
|
Historic statuses |
02 May 18 -
Request published |