12:01 11 Nov 25
Project:
3555 Waste Heat Recovery based 15 MW Power Generation Project at Bestway Cement Limited, Chakwal, Pakistan
- Request for post-registration changes
| Project | 3555 Waste Heat Recovery based 15 MW Power Generation Project at Bestway Cement Limited, Chakwal, Pakistan |
|---|---|
| PRC ref | PRC-3555-002 |
| Process track | Issuance |
| DOE | TÜV SÜD |
|
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes |
|
| Methodology(ies) list | |
| Standardized baseline(s) list | |
| DOE conducted validation of the changes | When performing a verification for the project activity or PoA stated above (See footnote 1 below) |
| Type of submission |
Changes to the project or programme design
|
| Applicable crediting period | 28 Aug 10 - 27 Aug 20 |
| Assessment opinion |
Assessment opinion (1214 KB)
|
| Revised PDD |
Revised PDD (1281 KB)
Revised PDD - track changes (1289 KB)
|
| Supplementary documents | |
| Signed form |
Signed form (495 KB)
|
| DOE clarification | |
| VVS version | VVS 2.0 |
| Current status | 22 May 14 -
Approved
Effective approval date: 22 May 14
|
| Historic statuses |
24 Apr 14 -
Request published |

Assessment opinion
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: