Project: 5947 CTL Landfill Gas Project - Request for post-registration changes
Project 5947 CTL Landfill Gas Project
PRC ref PRC-5947-007
Process track Issuance
DOE RINA
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
Methodology(ies) list
Standardized baseline(s) list
DOE conducted validation of the changes When performing a verification for the project activity or PoA stated above (See footnote 1 below)
Type of submission Temporary deviations from the monitoring plan or the monitoring methodology
  • Applicable period for proposed deviations (inclusive): 01 Apr 2020 - 31 Dec 2020
Assessment opinion Assessment opinion (512 KB)
Revised PDD  
Supplementary documents
Signed form Signed form (148 KB)
DOE clarification
VVS version VVS-PA 2.0
Current status 10 Jun 21 - Approved
Effective approval date: 10 Jun 21
Historic statuses 12 May 21 - Request published