Project:
0570 11.35 MW Grid Connected Wind Electricity Project at Pohra (Rajasthan) in India
- Request for post-registration changes
| Project | 0570 11.35 MW Grid Connected Wind Electricity Project at Pohra (Rajasthan) in India |
|---|---|
| PRC ref | PRC-0570-001 |
| Process track | Issuance |
| DOE | BVI |
|
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes |
|
| Methodology(ies) list | |
| Standardized baseline(s) list | |
| DOE conducted validation of the changes | When performing a verification for the project activity or PoA stated above (See footnote 1 below) |
| Type of submission |
Changes to the project or programme design
|
| Applicable crediting period | 29 Sep 03 - 28 Sep 13 |
| Assessment opinion |
Assessment opinion (134 KB)
|
| Revised PDD |
Revised PDD (481 KB)
Revised PDD - track changes (514 KB)
|
| Supplementary documents | |
| Signed form |
Signed form (1306 KB)
|
| DOE clarification | |
| VVS version | VVS 2.0 |
| Current status | 25 Apr 13 -
Approved
Effective approval date: 25 Apr 13
|
| Historic statuses |
27 Mar 13 -
Request published |

Assessment opinion