05:38 22 Feb 25
Project:
9954 Santa Teresa Hydropower Plant
- Request for post-registration changes
Project | 9954 Santa Teresa Hydropower Plant |
---|---|
PRC ref | PRC-9954-001 |
Process track | Prior approval |
DOE | ICONTEC |
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes |
No changes |
Methodology(ies) list | |
Standardized baseline(s) list | |
DOE conducted validation of the changes | Prior to commencement of a verification for the project activity or PoA stated above |
Type of submission |
Corrections that do not affect project design
Changes to the project or programme design
|
Applicable crediting period | 01 Sep 15 - 31 Aug 22 |
Assessment opinion |
![]() |
Revised PDD |
![]() ![]() |
Supplementary documents | |
Signed form |
![]() |
DOE clarification |
|
VVS version | VVS-PA 3.0 |
Current status | 16 Jan 24 -
Approved
Effective approval date: 15 Jan 24
|
Historic statuses |
28 Nov 23 -
Published 12 Dec 23 - Awaiting DOE clarifications 18 Dec 23 - DOE clarifications received 18 Dec 23 - Summary note being prepared 26 Dec 23 - Awaiting EB decision |
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: