Project: 3486 Goiandira, Pedra do Garrafão, Pirapetinga and Sítio Grande Small Hydropower Plants Project Activity - Request for post-registration changes
Project 3486 Goiandira, Pedra do Garrafão, Pirapetinga and Sítio Grande Small Hydropower Plants Project Activity
PRC ref PRC-3486-001
Process track Issuance
DOE PJRCES
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
Methodology(ies) list
Standardized baseline(s) list
DOE conducted validation of the changes When performing a verification for the project activity or PoA stated above (See footnote 1 below)
Type of submission Changes to the project or programme design
  • Changes have an impact on: None of the above
Applicable crediting period 24 Jan 11 - 23 Jan 18
Assessment opinion Assessment opinion (2015 KB)
Revised PDD Revised PDD (1177 KB)   Revised PDD - track changes (1220 KB)
Supplementary documents
Signed form Signed form (108 KB)
DOE clarification
VVS version VVS 2.0
Current status 27 Mar 15 - Approved
Effective approval date: 27 Mar 15
Historic statuses 26 Feb 15 - Request published