Project: 5947 CTL Landfill Gas Project - Request for post-registration changes
Project 5947 CTL Landfill Gas Project
PRC ref PRC-5947-005
Process track Prior approval
DOE RINA
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
No changes
Methodology(ies) list
Standardized baseline(s) list
DOE conducted validation of the changes Prior to commencement of a verification for the project activity or PoA stated above
Type of submission Corrections that do not affect project design
  • All changes are in Appendix 1 of the CDM project standard?

Changes to the project or programme design
  • Changes have an impact on: None of the above
Applicable crediting period 01 Apr 13 - 31 Mar 20
Assessment opinion Assessment opinion (671 KB)
Revised PDD Revised PDD (2258 KB)   Revised PDD - track changes (2460 KB)
Supplementary documents Appendix 1 - CTL Cash Flow PRC v9 2019 10 02 - Updated All FES.xlsx (401 KB)
Appendix 2 - CTL Cash Flow PRC v9 2019 10 02 only selling LFG Updated FES.xlsx (380 KB)
Appendix 3 - EcoUrbis PRC3 CER Spreadsheet 2019 09 04 FES.xls (629 KB)
Signed form Signed form (591 KB)
DOE clarification
VVS version VVS-PA 2.0
Current status 03 Jan 20 - Approved
Effective approval date: 02 Jan 20
Historic statuses 02 Dec 19 - Published
02 Dec 19 - Summary note being prepared
13 Dec 19 - Awaiting EB decision