Project: 10690 102 MW Gulpur Hydropower Project - Request for post-registration changes
Project 10690 102 MW Gulpur Hydropower Project
PRC ref PRC-10690-001
Process track Issuance
DOE KTR
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
No changes
Methodology(ies) list
Standardized baseline(s) list
DOE conducted validation of the changes When performing a verification for the project activity or PoA stated above (See footnote 1 below)
Type of submission Corrections that do not affect project design
  • All changes are in Appendix 1 of the CDM project standard?

Permanent changes from the monitoring plan or the monitoring methodology
  • All changes are in Appendix 1 of the CDM project standard?
Applicable crediting period 01 Sep 21 - 31 Aug 28
Assessment opinion Assessment opinion (1350 KB)
Revised PDD Revised PDD (2473 KB)   Revised PDD - track changes (2477 KB)
Supplementary documents
Signed form Signed form (59 KB)
DOE clarification
VVS version VVS-PA 3.0
Current status 15 Mar 23 - Request published