Project:
9550 Mwenga Hydro Power Project
- Request for post-registration changes
Project | 9550 Mwenga Hydro Power Project |
---|---|
PRC ref | PRC-9550-002 |
Process track | Issuance |
DOE | TÜV NORD |
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes |
|
Methodology(ies) list | |
Standardized baseline(s) list | |
DOE conducted validation of the changes | When performing a verification for the project activity or PoA stated above (See footnote 1 below) |
Type of submission |
Corrections that do not affect project design
Permanent changes from the monitoring plan or the monitoring methodology
Changes to the project or programme design
|
Applicable crediting period | 30 Jan 13 - 29 Jan 20 |
Assessment opinion | Assessment opinion (524 KB) |
Revised PDD | Revised PDD (4529 KB) Revised PDD - track changes (2000 KB) |
Supplementary documents | |
Signed form | Signed form (174 KB) |
DOE clarification | |
VVS version | VVS-PA 2.0 |
Current status | 25 Jul 19 -
Approved
Effective approval date: 25 Jul 19
|
Historic statuses |
26 Jun 19 -
Request published |