Project: 2819 50.4 MW Tata Wind Farm - in Maharashtra - Request for post-registration changes
Project 2819 50.4 MW Tata Wind Farm - in Maharashtra
PRC ref PRC-2819-001
Process track Prior approval
DOE SGS
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
Methodology(ies) list
Standardized baseline(s) list
DOE conducted validation of the changes Prior to commencement of a verification for the project activity or PoA stated above
Type of submission Corrections that do not affect project design
  • All changes are in Appendix 1 of the CDM project standard? Yes

Permanent changes from the monitoring plan or the monitoring methodology
  • All changes are in Appendix 1 of the CDM project standard? No
Applicable crediting period 01 Jun 10 - 31 May 20
Assessment opinion Assessment opinion (275 KB)
Revised PDD Revised PDD (1953 KB)   Revised PDD - track changes (1984 KB)
Supplementary documents
Signed form Signed form (45 KB)
DOE clarification
VVS version VVS 2.0
Current status 25 Sep 13 - Approved
Effective approval date: 22 Sep 13
Historic statuses 13 Aug 13 - Published
13 Aug 13 - Summary note being prepared
01 Sep 13 - Awaiting EB decision