Project: 0931 San Carlos Renewable Energy Project - Request for post-registration changes
Project 0931 San Carlos Renewable Energy Project
PRC ref PRC-0931-001
Process track Prior approval
DOE TÜV NORD
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
Methodology(ies) list
Standardized baseline(s) list
DOE conducted validation of the changes When performing a verification for the project activity or PoA stated above (See footnote 1 below)
Type of submission Permanent changes from the monitoring plan or the monitoring methodology
  • All changes are in Appendix 1 of the CDM project standard? No

Changes to the project or programme design
  • Changes have an impact on: None of the above
Applicable crediting period 01 Nov 08 - 31 Oct 15
Assessment opinion Assessment opinion (808 KB)
Revised PDD Revised PDD (675 KB)   Revised PDD - track changes (694 KB)
Supplementary documents
Signed form Signed form (52 KB)
DOE clarification
VVS version VVS 2.0
Current status 08 Jul 13 - Approved
Effective approval date: 07 Jul 13
Historic statuses 04 Jun 13 - Published
04 Jun 13 - Summary note being prepared
17 Jun 13 - Awaiting EB decision