09:23 25 Jan 25
Project:
3064 Wuhe Kaidi Biomass Power Project
- Request for post-registration changes
Project | 3064 Wuhe Kaidi Biomass Power Project |
---|---|
PRC ref | PRC-3064-001 |
Process track | Issuance |
DOE | CEC |
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes |
|
Methodology(ies) list | |
Standardized baseline(s) list | |
DOE conducted validation of the changes | When performing a verification for the project activity or PoA stated above (See footnote 1 below) |
Type of submission |
Corrections that do not affect project design
Changes to the project or programme design
|
Applicable crediting period | 15 Jan 11 - 14 Jan 18 |
Assessment opinion | Assessment opinion (478 KB) |
Revised PDD | Revised PDD (1451 KB) Revised PDD - track changes (1482 KB) |
Supplementary documents |
Appendix 1 - Wuhe-ER-notification.xls (37 KB)
Appendix 2 - irr-wuhe.xls (144 KB) |
Signed form | Signed form (374 KB) |
DOE clarification | |
VVS version | VVS 2.0 |
Current status | 19 Feb 14 -
Approved
Effective approval date: 19 Feb 14
|
Historic statuses |
21 Jan 14 -
Request published |