15:28 25 Jun 25
Project:
0984 Golden Hope Composting Project - Lavang
- Request for post-registration changes
Project | 0984 Golden Hope Composting Project - Lavang |
---|---|
PRC ref | PRC-0984-001 |
Process track | Prior approval |
DOE | DNV |
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes |
|
Methodology(ies) list | |
Standardized baseline(s) list | |
DOE conducted validation of the changes | When performing a verification for the project activity or PoA stated above (See footnote 1 below) |
Type of submission |
Temporary deviations from the monitoring plan or the monitoring methodology
Corrections that do not affect project design
Permanent changes from the monitoring plan or the monitoring methodology
Changes to the project or programme design
|
Applicable crediting period | 14 Dec 07 - 13 Dec 14 |
Assessment opinion |
![]() |
Revised PDD |
![]() ![]() |
Supplementary documents | |
Signed form |
![]() |
DOE clarification |
![]() ![]() ![]() |
VVS version | VVS 2.0 |
Current status | 27 Sep 12 -
Approved
Effective approval date: 27 Sep 12
|
Historic statuses |
24 Jul 12 -
Published 13 Aug 12 - Awaiting DOE clarifications 27 Aug 12 - DOE clarifications received 27 Aug 12 - Summary note being prepared 06 Sep 12 - Awaiting EB decision |
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: