Project:
0788 Korea South-East Power Co. (KOSEP) small scale hydroelectric power plants project(The Samchonpo Thermal Power Plant and Younghung Thermal Power plant small scale hydroelectric power plants construction project)
- Request for post-registration changes
Project | 0788 Korea South-East Power Co. (KOSEP) small scale hydroelectric power plants project(The Samchonpo Thermal Power Plant and Younghung Thermal Power plant small scale hydroelectric power plants construction project) |
---|---|
PRC ref | PRC-0788-001 |
Process track | Issuance |
DOE | KSA |
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes |
|
Methodology(ies) list | |
Standardized baseline(s) list | |
DOE conducted validation of the changes | When performing a verification for the project activity or PoA stated above (See footnote 1 below) |
Type of submission |
Changes to the project or programme design
|
Applicable crediting period | 01 Nov 07 - 31 Oct 17 |
Assessment opinion | Assessment opinion (547 KB) |
Revised PDD | Revised PDD (1110 KB) Revised PDD - track changes (1113 KB) |
Supplementary documents |
Appendix 1 - revised Investment Analysis.xls (26 KB)
|
Signed form | Signed form (128 KB) |
DOE clarification | |
VVS version | VVS 2.0 |
Current status | 25 Jan 13 -
Approved
Effective approval date: 25 Jan 13
|
Historic statuses |
27 Dec 12 -
Request published |