Project: 9042 Small Hydro Power Plants Santa Gabriela and Planalto - Request for post-registration changes
Project 9042 Small Hydro Power Plants Santa Gabriela and Planalto
PRC ref PRC-9042-001
Process track Prior approval
DOE RINA
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
No changes
Methodology(ies) list
Standardized baseline(s) list
DOE conducted validation of the changes Prior to commencement of a verification for the project activity or PoA stated above
Type of submission Corrections that do not affect project design
  • All changes are in Appendix 1 of the CDM project standard?

Permanent changes from the monitoring plan or the monitoring methodology
  • All changes are in Appendix 1 of the CDM project standard?

Changes to the project or programme design
  • Changes have an impact on: Decrease in the capacity, Removal or addition of sites, Actual operational parameters differ from the expected parameters
Applicable crediting period 01 Jul 13 - 30 Jun 20
Assessment opinion Assessment opinion (650 KB)
Revised PDD Revised PDD (1287 KB)   Revised PDD - track changes (1532 KB)
Supplementary documents Appendix 1 - 9042 Cash Flow PCH Planalto.v1.2.xlsx (1464 KB)
Appendix 2 - 9042 CER Calculation PDD-2025-rev3.xlsx (35 KB)
Appendix 3 - 9042 Common Practice Analysis-2025-rev2.xlsx (858 KB)
Signed form Signed form (235 KB)
DOE clarification
VVS version VVS-PA 3.0
Current status 17 Nov 25 - Awaiting EB decision
Historic statuses 03 Nov 25 - Published
03 Nov 25 - Summary note being prepared