17:38 22 Jan 26
Project:
0999 119.8 MW Natural Gas based Combined Cycle Power Plant, at Tanjavur, Tamilnadu by M/s Aban Power Company Limited
- Request for post-registration changes
| Project | 0999 119.8 MW Natural Gas based Combined Cycle Power Plant, at Tanjavur, Tamilnadu by M/s Aban Power Company Limited |
|---|---|
| PRC ref | PRC-0999-001 |
| Process track | Prior approval |
| DOE | SGS |
|
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes |
|
| Methodology(ies) list | |
| Standardized baseline(s) list | |
| DOE conducted validation of the changes | When performing a verification for the project activity or PoA stated above (See footnote 1 below) |
| Type of submission |
Corrections that do not affect project design
Permanent changes from the monitoring plan or the monitoring methodology
|
| Applicable crediting period | 01 Jan 06 - 31 Dec 15 |
| Assessment opinion |
Assessment opinion (253 KB)
|
| Revised PDD |
Revised PDD (519 KB)
Revised PDD - track changes (608 KB)
|
| Supplementary documents | |
| Signed form |
Signed form (134 KB)
|
| DOE clarification | |
| VVS version | VVS 2.0 |
| Current status | 22 Feb 13 -
Approved
Effective approval date: 20 Feb 13
|
| Historic statuses |
29 Jan 13 -
Published 29 Jan 13 - Summary note being prepared 31 Jan 13 - Awaiting EB decision |

Assessment opinion
Offset now: visit the United Nations Carbon Offset Platform