02:11 12 Nov 25
Project:
3505 Dak Rung Hydropower Project
- Request for post-registration changes
| Project | 3505 Dak Rung Hydropower Project |
|---|---|
| PRC ref | PRC-3505-001 |
| Process track | Issuance |
| DOE | TÜV NORD |
|
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes |
|
| Methodology(ies) list | |
| Standardized baseline(s) list | |
| DOE conducted validation of the changes | When performing a verification for the project activity or PoA stated above (See footnote 1 below) |
| Type of submission |
Corrections that do not affect project design
Permanent changes from the monitoring plan or the monitoring methodology
|
| Applicable crediting period | 04 Sep 10 - 03 Sep 17 |
| Assessment opinion |
Assessment opinion (552 KB)
|
| Revised PDD |
Revised PDD (845 KB)
Revised PDD - track changes (761 KB)
|
| Supplementary documents | |
| Signed form |
Signed form (52 KB)
|
| DOE clarification | |
| VVS version | VVS 2.0 |
| Current status | 09 Aug 13 -
Approved
Effective approval date: 09 Aug 13
|
| Historic statuses |
11 Jul 13 -
Request published |

Assessment opinion
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: