Project: 3179 Jincheng Chengzhuang 18 MW coal mine methane power generation project - Request for post-registration changes
Project 3179 Jincheng Chengzhuang 18 MW coal mine methane power generation project
PRC ref PRC-3179-001
Process track Prior approval
DOE ERM CVS
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
Methodology(ies) list
Standardized baseline(s) list
DOE conducted validation of the changes When performing a verification for the project activity or PoA stated above (See footnote 1 below)
Type of submission Permanent changes from the monitoring plan or the monitoring methodology
  • All changes are in Appendix 1 of the CDM project standard? No

Changes to the project or programme design
  • Changes have an impact on: None of the above
Applicable crediting period 02 Dec 10 - 01 Dec 20
Assessment opinion Assessment opinion (185 KB)
Revised PDD Revised PDD (986 KB)   Revised PDD - track changes (1019 KB)
Supplementary documents
Signed form Signed form (2373 KB)
DOE clarification




DOE clarification 6 - CCC_Jincheng_VO_Approval of Changes_13Nov2012_signed.pdf (189 KB)
DOE clarification 7 - CCC_PRC Cla DOE response_13Nov2012signed.pdf (51 KB)
VVS version VVS 2.0
Current status 18 Dec 12 - Approved
Effective approval date: 18 Dec 12
Historic statuses 17 Oct 12 - Published
31 Oct 12 - Awaiting DOE clarifications
13 Nov 12 - DOE clarifications received
13 Nov 12 - Summary note being prepared
27 Nov 12 - Awaiting EB decision