Project: 6762 Methane Capture and Utilization Project at Carotino Palm Oil Mill, Malaysia - Request for post-registration changes
Project 6762 Methane Capture and Utilization Project at Carotino Palm Oil Mill, Malaysia
PRC ref PRC-6762-003
Process track Issuance
DOE TÜV SÜD
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
No changes
Methodology(ies) list
Standardized baseline(s) list
DOE conducted validation of the changes When performing a verification for the project activity or PoA stated above (See footnote 1 below)
Type of submission Temporary deviations from the monitoring plan or the monitoring methodology
  • Applicable period for proposed deviations (inclusive): 01 Jan 2020 - 31 Dec 2020
Assessment opinion Assessment opinion (378 KB)
Revised PDD  
Supplementary documents Appendix 1 - 6762_Carotino_MR 01012020 to 31122020_v2_Rev2_050324.pdf (872 KB)
Appendix 2 - 6762_Carotino_ER cal_v2_01012020 to 31122020_Rev2 (1).xlsx (259 KB)
Signed form Signed form (160 KB)
DOE clarification
VVS version VVS-PA 3.0
Current status 31 Oct 24 - Approved
Effective approval date: 31 Oct 24
Historic statuses 02 Oct 24 - Request published