Project: 9791 BQS improved cookstoves for Burundi’s schools - Request for post-registration changes
Project 9791 BQS improved cookstoves for Burundi’s schools
PRC ref PRC-9791-001
Process track Issuance
DOE LGAI Tech. Center S.A
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
Methodology(ies) list
Standardized baseline(s) list
DOE conducted validation of the changes When performing a verification for the project activity or PoA stated above (See footnote 1 below)
Type of submission Corrections that do not affect project design
  • All changes are in Appendix 1 of the CDM project standard?

Permanent changes from the monitoring plan or the monitoring methodology
  • All changes are in Appendix 1 of the CDM project standard? Yes

Changes to the project or programme design
  • Changes have an impact on: None of the above
Applicable crediting period 25 Jan 16 - 24 Jan 23
Assessment opinion Assessment opinion (220 KB)
Revised PDD Revised PDD (1014 KB)   Revised PDD - track changes (1243 KB)
Supplementary documents Appendix 1 - 200921 - ER Ex-ante Calc - BQSSCH - (ID 10543).xls (617 KB)
Signed form Signed form (52 KB)
DOE clarification
VVS version VVS-PA 2.0
Current status 07 Apr 21 - Rejected
Effective rejection date: 07 Apr 21. The reason for rejection can be viewed as part of the final ruling for the associated request for issuance.
Historic statuses 09 Dec 20 - Request published