Project: 9111 7 MW Bundled Hydro power project at Himachal Pradesh of Raajratna Energy Holdings Pvt. Ltd - Request for post-registration changes
Project 9111 7 MW Bundled Hydro power project at Himachal Pradesh of Raajratna Energy Holdings Pvt. Ltd
PRC ref PRC-9111-001
Process track Issuance
DOE URS
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
No changes
Methodology(ies) list
Standardized baseline(s) list
DOE conducted validation of the changes When performing a verification for the project activity or PoA stated above (See footnote 1 below)
Type of submission Corrections that do not affect project design
  • All changes are in Appendix 1 of the CDM project standard? Yes
Applicable crediting period 01 Jan 13 - 31 Dec 22
Assessment opinion Assessment opinion (88 KB)
Revised PDD Revised PDD (346 KB)   Revised PDD - track changes (353 KB)
Supplementary documents
Signed form Signed form (4048 KB)
DOE clarification
VVS version VVS 9.0
Current status 30 Dec 16 - Approved
Effective approval date: 30 Dec 16
Historic statuses 01 Dec 16 - Request published