Project: 4547 Ambuklao Hydro Electric Power Plant (AHEPP) rehabilitation project - Request for post-registration changes
Project 4547 Ambuklao Hydro Electric Power Plant (AHEPP) rehabilitation project
PRC ref PRC-4547-002
Process track Issuance
DOE TÜV NORD
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
Methodology(ies) list
Standardized baseline(s) list
DOE conducted validation of the changes When performing a verification for the project activity or PoA stated above (See footnote 1 below)
Type of submission Permanent changes from the monitoring plan or the monitoring methodology
  • All changes are in Appendix 1 of the CDM project standard? Yes
Applicable crediting period 01 Jun 11 - 31 May 18
Assessment opinion Assessment opinion (381 KB)
Revised PDD Revised PDD (1285 KB)   Revised PDD - track changes (1513 KB)
Supplementary documents
Signed form Signed form (47 KB)
DOE clarification
VVS version VVS 2.0
Current status 20 Nov 14 - Approved
Effective approval date: 20 Nov 14
Historic statuses 22 Oct 14 - Request published