Project: 0346 Nueva Aldea Biomass Power Plant Phase 2 - Request for post-registration changes
Project 0346 Nueva Aldea Biomass Power Plant Phase 2
PRC ref PRC-0346-004
Process track Issuance
DOE Earthood
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
No changes
Methodology(ies) list
Standardized baseline(s) list
DOE conducted validation of the changes When performing a verification for the project activity or PoA stated above (See footnote 1 below)
Type of submission Temporary deviations from the monitoring plan or the monitoring methodology
  • Applicable period for proposed deviations (inclusive): 01 Jan 2016 - 31 Dec 2017
Assessment opinion Assessment opinion (412 KB)
Revised PDD  
Supplementary documents
Signed form Signed form (247 KB)
DOE clarification
VVS version VVS-PA 2.0
Current status 16 Apr 20 - Approved
Effective approval date: 16 Apr 20
Historic statuses 18 Mar 20 - Request published