08:09 21 Jan 26
Project:
4118 Asahan 1 Hydroelectric Power Plant 2 x 90 MW
- Request for post-registration changes
| Project | 4118 Asahan 1 Hydroelectric Power Plant 2 x 90 MW |
|---|---|
| PRC ref | PRC-4118-003 |
| Process track | Issuance |
| DOE | ERM CVS |
|
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes |
No changes |
| Methodology(ies) list | |
| Standardized baseline(s) list | |
| DOE conducted validation of the changes | When performing a verification for the project activity or PoA stated above (See footnote 1 below) |
| Type of submission |
Temporary deviations from the monitoring plan or the monitoring methodology
|
| Assessment opinion |
Assessment opinion (99 KB)
|
| Revised PDD | |
| Supplementary documents | |
| Signed form |
Signed form (223 KB)
|
| DOE clarification | |
| VVS version | VVS 2.0 |
| Current status | 21 Apr 17 -
Approved
Effective approval date: 21 Apr 17
|
| Historic statuses |
23 Mar 17 -
Request published |

Assessment opinion
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: