07:05 23 Dec 24
Project:
5962 International water purification programme
- Request for post-registration changes
Project | 5962 International water purification programme |
---|---|
PRC ref | PRC-5962-007 |
Process track | Prior approval |
DOE | CCSC |
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes |
Change a version of methodology |
Methodology(ies) list |
AMS-III.AV. ver. 5 -
Low greenhouse gas emitting safe drinking water production systems
|
Standardized baseline(s) list | |
DOE conducted validation of the changes | Prior to commencement of a verification for the project activity or PoA stated above |
Type of submission |
Permanent changes from the monitoring plan or the monitoring methodology
Changes to the project or programme design
|
Applicable crediting period | 16 Nov 12 - 15 Nov 19 |
Assessment opinion | Assessment opinion (594 KB) |
Revised PDD | Revised PDD (2293 KB) Revised PDD - track changes (2368 KB) |
Supplementary documents |
Appendix 1 - PRC Validation Report_POA-DD5962_v3_tc.pdf (599 KB)
|
Signed form | Signed form (56 KB) |
DOE clarification |
DOE clarification 1 - Clarification_PRC5962-007.pdf (99 KB)
|
VVS version | VVS-PoA 2.0 |
Current status | 25 Jul 19 -
Approved
Effective approval date: 23 Jul 19
|
Historic statuses |
20 May 19 -
Published 03 Jun 19 - Awaiting DOE clarifications 17 Jun 19 - DOE clarifications received 17 Jun 19 - Summary note being prepared 02 Jul 19 - Awaiting EB decision |
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: