23:38 10 Nov 25
Project:
3816 Guanaquitas 9.74 MW Hydroelectric project
- Request for post-registration changes
| Project | 3816 Guanaquitas 9.74 MW Hydroelectric project |
|---|---|
| PRC ref | PRC-3816-002 |
| Process track | Renewal |
| DOE | TÜV NORD |
|
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes |
No changes |
| Methodology(ies) list |
AMS-I.D. ver. 18 -
Grid connected renewable electricity generation
|
| Standardized baseline(s) list | |
| DOE conducted validation of the changes | Combined with a request for renewal of crediting period (See footnote 2 below) |
| Type of submission |
Permanent changes from the monitoring plan or the monitoring methodology
|
| Applicable crediting period | 03 Oct 20 - 02 Oct 27 |
| Assessment opinion |
Assessment opinion (627 KB)
|
| Revised PDD |
Revised PDD - track changes (1621 KB)
|
| Supplementary documents | |
| Signed form |
Signed form (339 KB)
|
| DOE clarification | |
| VVS version | VVS-PA 2.0 |
| Current status | 20 Dec 21 -
Approved
Effective approval date: 20 Dec 21
|
| Historic statuses |
20 Nov 21 -
Request published |

Assessment opinion
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: