Project: 3416 Antu Gudonghe I Hydro Power Project - Request for post-registration changes
Project 3416 Antu Gudonghe I Hydro Power Project
PRC ref PRC-3416-001
Process track Issuance
DOE TÜV NORD
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
Methodology(ies) list
Standardized baseline(s) list
DOE conducted validation of the changes When performing a verification for the project activity or PoA stated above (See footnote 1 below)
Type of submission Permanent changes from the monitoring plan or the monitoring methodology
  • All changes are in Appendix 1 of the CDM project standard? Yes
Applicable crediting period 18 May 11 - 17 May 18
Assessment opinion Assessment opinion (396 KB)
Revised PDD Revised PDD (553 KB)   Revised PDD - track changes (553 KB)
Supplementary documents
Signed form Signed form (46 KB)
DOE clarification
VVS version VVS 2.0
Current status 01 Feb 13 - Approved
Effective approval date: 01 Feb 13
Historic statuses 03 Jan 13 - Request published