22:35 13 Sep 24
Project:
0453 NorthWind Bangui Bay Project
- Request for post-registration changes
Project | 0453 NorthWind Bangui Bay Project |
---|---|
PRC ref | PRC-0453-002 |
Process track | Prior approval |
DOE | AENOR |
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes |
|
Methodology(ies) list | |
Standardized baseline(s) list | |
DOE conducted validation of the changes | When performing a verification for the project activity or PoA stated above (See footnote 1 below) |
Type of submission |
Corrections that do not affect project design
Permanent changes from the monitoring plan or the monitoring methodology
|
Applicable crediting period | 01 May 05 - 30 Apr 12 |
Assessment opinion | Assessment opinion (283 KB) |
Revised PDD | Revised PDD (1103 KB) Revised PDD - track changes (1408 KB) |
Supplementary documents | |
Signed form | Signed form (413 KB) |
DOE clarification | |
VVS version | VVS 2.0 |
Current status | 09 Jun 14 -
Approved
Effective approval date: 06 Jun 14
|
Historic statuses |
14 May 14 -
Published 14 May 14 - Summary note being prepared 16 May 14 - Awaiting EB decision |