Project: 7756 Georgia: Refurbishment of Enguri Hydro Power Plant - Request for post-registration changes
Project 7756 Georgia: Refurbishment of Enguri Hydro Power Plant
PRC ref PRC-7756-001
Process track Prior approval
DOE TÜV NORD
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
Methodology(ies) list
Standardized baseline(s) list
DOE conducted validation of the changes Prior to commencement of a verification for the project activity or PoA stated above
Type of submission Permanent changes from the monitoring plan or the monitoring methodology
  • All changes are in Appendix 1 of the CDM project standard? No

Changes to the project or programme design
  • Changes have an impact on: None of the above
Applicable crediting period 01 Jan 13 - 31 Dec 22
Assessment opinion Assessment opinion (333 KB)
Revised PDD Revised PDD (993 KB)   Revised PDD - track changes (1020 KB)
Supplementary documents
Signed form Signed form (54 KB)
DOE clarification
VVS version VVS 2.0
Current status 26 Mar 14 - Approved
Effective approval date: 26 Mar 14
Historic statuses 18 Feb 14 - Published
18 Feb 14 - Summary note being prepared
05 Mar 14 - Awaiting EB decision