Project: 6715 Chancay Hydroelectric Power Plant - Request for post-registration changes
Project 6715 Chancay Hydroelectric Power Plant
PRC ref PRC-6715-001
Process track Issuance
DOE ICONTEC
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
No changes
Methodology(ies) list
Standardized baseline(s) list
DOE conducted validation of the changes When performing a verification for the project activity or PoA stated above (See footnote 1 below)
Type of submission Corrections that do not affect project design
  • All changes are in Appendix 1 of the CDM project standard?

Changes to the project or programme design
  • Changes have an impact on: Actual operational parameters differ from the expected parameters
Applicable crediting period 01 Jan 16 - 31 Dec 22
Assessment opinion Assessment opinion (367 KB)
Revised PDD Revised PDD (3912 KB)   Revised PDD - track changes (4067 KB)
Supplementary documents
Signed form Signed form (2288 KB)
DOE clarification
VVS version VVS-PA 3.0
Current status 05 Jan 23 - Approved
Effective approval date: 05 Jan 23
Historic statuses 07 Dec 22 - Request published