19:25 13 Nov 25
Project:
2938 Power Prospect 9.9MW Rice Husk Power Plant
- Request for post-registration changes
| Project | 2938 Power Prospect 9.9MW Rice Husk Power Plant |
|---|---|
| PRC ref | PRC-2938-001 |
| Process track | Prior approval |
| DOE | JQA |
|
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes |
|
| Methodology(ies) list | |
| Standardized baseline(s) list | |
| DOE conducted validation of the changes | When performing a verification for the project activity or PoA stated above (See footnote 1 below) |
| Type of submission |
Permanent changes from the monitoring plan or the monitoring methodology
Changes to the project or programme design
|
| Applicable crediting period | 25 Feb 10 - 24 Feb 17 |
| Assessment opinion |
Assessment opinion (455 KB)
|
| Revised PDD |
Revised PDD (1970 KB)
Revised PDD - track changes (2006 KB)
|
| Supplementary documents | |
| Signed form |
Signed form (782 KB)
|
| DOE clarification | |
| VVS version | VVS 2.0 |
| Current status | 18 Sep 13 -
Approved
Effective approval date: 15 Sep 13
|
| Historic statuses |
13 Aug 13 -
Published 13 Aug 13 - Summary note being prepared 26 Aug 13 - Awaiting EB decision |

Assessment opinion