Project: 0373 São João Landfill Gas to Energy Project (SJ) - Request for post-registration changes
Project 0373 São João Landfill Gas to Energy Project (SJ)
PRC ref PRC-0373-001
Process track Prior approval
DOE RINA
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
Change a version of methodology
Methodology(ies) list ACM0001 ver. 18 - Flaring or use of landfill gas
Standardized baseline(s) list
DOE conducted validation of the changes Prior to commencement of a verification for the project activity or PoA stated above
Type of submission Temporary deviations from the monitoring plan or the monitoring methodology
  • Applicable period for proposed deviations (inclusive): 16 May 2012 - 21 May 2014

Corrections that do not affect project design
  • All changes are in Appendix 1 of the CDM project standard?

Permanent changes from the monitoring plan or the monitoring methodology
  • All changes are in Appendix 1 of the CDM project standard? Yes

Changes to the project or programme design
  • Changes have an impact on: Addition of new components or extension/addition of technologies/measures that introduce:, Voluntary update of the applied methodologies to a later valid version or voluntary change to other methodologies
Applicable crediting period 22 May 07 - 21 May 14
Assessment opinion Assessment opinion (1018 KB)
Revised PDD Revised PDD (1628 KB)   Revised PDD - track changes (2828 KB)
Supplementary documents Appendix 1 - 20190606_São João_CERs_v.4.xlsx (205 KB)
Appendix 2 - 20190729_Enclosure 1_Rev3.xlsx (633 KB)
Appendix 3 - 20190729_Enclosure 1_Rev3-original.xls (2244 KB)
Appendix 4 - Appendix 3 - Enclosure 2 - actual_v.2.xls (83 KB)
Appendix 5 - SJEA_Estimative Vs. Performed.xlsx (117 KB)
Signed form Signed form (174 KB)
DOE clarification DOE clarification 1 - FVRP_2018BQ35MD_4_0Aa_02_10_2019_approved.pdf (1018 KB)


VVS version VVS-PA 2.0
Current status 13 Nov 19 - Approved
Effective approval date: 12 Nov 19
Historic statuses 08 Jul 19 - Published
20 Sep 19 - Awaiting DOE clarifications
03 Oct 19 - DOE clarifications received
03 Oct 19 - Summary note being prepared
23 Oct 19 - Awaiting EB decision