Project: 9741 Cabo Leones Wind Farm - Request for post-registration changes
Project 9741 Cabo Leones Wind Farm
PRC ref PRC-9741-002
Process track Prior approval
DOE Earthood
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
Methodology(ies) list
Standardized baseline(s) list
DOE conducted validation of the changes When performing a verification for the project activity or PoA stated above (See footnote 1 below)
Type of submission Changes to the project or programme design
  • Changes have an impact on: Increase in the capacity, Confirmation that the submission of this form is within two years of the commissioning or implementation, whichever is later

Change to the start date of the crediting period
  • Proposed start date of crediting period: 12 Jun 2018
Applicable crediting period 12 Jun 18 - 11 Jun 25
Assessment opinion Assessment opinion (505 KB)
Revised PDD Revised PDD (2239 KB)   Revised PDD - track changes (2474 KB)
Supplementary documents Appendix 1 - CABO LEONES_ER Calculation_ex ante.xlsx (219 KB)
Appendix 2 - 211112 IRR_Cabo Leones.xls (650 KB)
Signed form Signed form (116 KB)
DOE clarification
VVS version VVS-PA 3.0
Current status 03 Feb 22 - Approved
Effective approval date: 02 Feb 22
Historic statuses 27 Dec 21 - Published
27 Dec 21 - Summary note being prepared
13 Jan 22 - Awaiting EB decision