Project:
2710 Generation of electricity from 3.3 MW installed capacity wind mills by Mission Biofuels India Private Limited (MBIPL), in Sangli District, Maharashtra, India
- Request for post-registration changes
Project | 2710 Generation of electricity from 3.3 MW installed capacity wind mills by Mission Biofuels India Private Limited (MBIPL), in Sangli District, Maharashtra, India |
---|---|
PRC ref | PRC-2710-001 |
Process track | Prior approval |
DOE | DNV |
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes |
|
Methodology(ies) list | |
Standardized baseline(s) list | |
DOE conducted validation of the changes | When performing a verification for the project activity or PoA stated above (See footnote 1 below) |
Type of submission |
Permanent changes from the monitoring plan or the monitoring methodology
Changes to the project or programme design
|
Applicable crediting period | 20 Jan 10 - 19 Jan 20 |
Assessment opinion | Assessment opinion (78 KB) |
Revised PDD | Revised PDD (350 KB) Revised PDD - track changes (456 KB) |
Supplementary documents | |
Signed form | Signed form (170 KB) |
DOE clarification | |
VVS version | VVS 2.0 |
Current status | 09 Sep 13 -
Approved
Effective approval date: 08 Aug 13
|
Historic statuses |
03 Jul 13 -
Published 03 Jul 13 - Summary note being prepared 18 Jul 13 - Awaiting EB decision |