06:16 06 Jul 25
Project:
0834 Egyptian Brick Factory GHG Reduction Project
- Request for post-registration changes
Project | 0834 Egyptian Brick Factory GHG Reduction Project |
---|---|
PRC ref | PRC-0834-001 |
Process track | Issuance |
DOE | TÜV NORD |
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes |
|
Methodology(ies) list | |
Standardized baseline(s) list | |
DOE conducted validation of the changes | When performing a verification for the project activity or PoA stated above (See footnote 1 below) |
Type of submission |
Corrections that do not affect project design
|
Applicable crediting period | 01 Mar 12 - 28 Feb 22 |
Assessment opinion |
![]() |
Revised PDD |
![]() ![]() |
Supplementary documents |
![]() ![]() |
Signed form |
![]() |
DOE clarification | |
VVS version | VVS 2.0 |
Current status | 15 May 14 -
Approved
Effective approval date: 15 May 14
|
Historic statuses |
16 Apr 14 -
Request published |
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: