Project: 0923 6.25 MW grid-connected Sattegala Mini Hydel Scheme at SLS Power Industries Ltd., in Chamarajanagar District, Karnataka - Request for post-registration changes
Project 0923 6.25 MW grid-connected Sattegala Mini Hydel Scheme at SLS Power Industries Ltd., in Chamarajanagar District, Karnataka
PRC ref PRC-0923-001
Process track Issuance
DOE TÜV NORD
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
Methodology(ies) list
Standardized baseline(s) list
DOE conducted validation of the changes When performing a verification for the project activity or PoA stated above (See footnote 1 below)
Type of submission Corrections that do not affect project design
  • All changes are in Appendix 1 of the CDM project standard? Yes

Permanent changes from the monitoring plan or the monitoring methodology
  • All changes are in Appendix 1 of the CDM project standard? Yes

Changes to the project or programme design
  • Changes have an impact on: None of the above
Applicable crediting period 24 Mar 07 - 23 Mar 14
Assessment opinion Assessment opinion (777 KB)
Revised PDD Revised PDD (535 KB)   Revised PDD - track changes (550 KB)
Supplementary documents
Signed form Signed form (54 KB)
DOE clarification
VVS version VVS 2.0
Current status 04 Oct 13 - Approved
Effective approval date: 04 Oct 13
Historic statuses 05 Sep 13 - Request published