06:26 14 Dec 24
Project:
9118 Hydro Electric Plant - Hidro Pantasma
- Request for post-registration changes
Project | 9118 Hydro Electric Plant - Hidro Pantasma |
---|---|
PRC ref | PRC-9118-001 |
Process track | Issuance |
DOE | TÜV NORD |
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes |
No changes |
Methodology(ies) list | |
Standardized baseline(s) list | |
DOE conducted validation of the changes | When performing a verification for the project activity or PoA stated above (See footnote 1 below) |
Type of submission |
Temporary deviations from the monitoring plan or the monitoring methodology
Corrections that do not affect project design
Permanent changes from the monitoring plan or the monitoring methodology
|
Applicable crediting period | 07 Oct 13 - 06 Oct 20 |
Assessment opinion | Assessment opinion (704 KB) |
Revised PDD | Revised PDD (1005 KB) Revised PDD - track changes (1076 KB) |
Supplementary documents | |
Signed form | Signed form (250 KB) |
DOE clarification | |
VVS version | VVS-PA 2.0 |
Current status | 12 Jan 22 -
Approved
Effective approval date: 12 Jan 22
|
Historic statuses |
14 Dec 21 -
Request published |