Project: 2650 Biogas project, BAJ Terbanggi - Request for post-registration changes
Project 2650 Biogas project, BAJ Terbanggi
PRC ref PRC-2650-001
Process track Issuance
DOE DNV
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
Methodology(ies) list
Standardized baseline(s) list
DOE conducted validation of the changes When performing a verification for the project activity or PoA stated above (See footnote 1 below)
Type of submission Temporary deviations from the monitoring plan or the monitoring methodology
  • Applicable period for proposed deviations (inclusive): 01 Jul 2011 - 31 Dec 2012
Assessment opinion Assessment opinion (115 KB)
Revised PDD  
Supplementary documents
Signed form Signed form (165 KB)
DOE clarification
VVS version VVS 2.0
Current status 20 Dec 13 - Approved
Effective approval date: 20 Dec 13
Historic statuses 21 Nov 13 - Request published