Project: 8756 Providencia I: 1.8MW Small Hydro Power Generation Plant - Request for post-registration changes
Project 8756 Providencia I: 1.8MW Small Hydro Power Generation Plant
PRC ref PRC-8756-001
Process track Issuance
DOE ICONTEC
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
No changes
Methodology(ies) list
Standardized baseline(s) list
DOE conducted validation of the changes When performing a verification for the project activity or PoA stated above (See footnote 1 below)
Type of submission Corrections that do not affect project design
  • All changes are in Appendix 1 of the CDM project standard?

Permanent changes from the monitoring plan or the monitoring methodology
  • All changes are in Appendix 1 of the CDM project standard? Yes

Changes to the project or programme design
  • Changes have an impact on: None of the above
Applicable crediting period 17 Feb 13 - 16 Feb 20
Assessment opinion Assessment opinion (368 KB)
Revised PDD Revised PDD (1478 KB)   Revised PDD - track changes (1709 KB)
Supplementary documents Appendix 1 - BD Calculo ER Providencia I_ver5 31082020 rJCC.xlsx (72 KB)
Signed form Signed form (147 KB)
DOE clarification
VVS version VVS-PA 2.0
Current status 31 Dec 20 - Approved
Effective approval date: 31 Dec 20
Historic statuses 02 Dec 20 - Request published