Project:
8756 Providencia I: 1.8MW Small Hydro Power Generation Plant
- Request for post-registration changes
| Project | 8756 Providencia I: 1.8MW Small Hydro Power Generation Plant |
|---|---|
| PRC ref | PRC-8756-001 |
| Process track | Issuance |
| DOE | ICONTEC |
|
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes |
No changes |
| Methodology(ies) list | |
| Standardized baseline(s) list | |
| DOE conducted validation of the changes | When performing a verification for the project activity or PoA stated above (See footnote 1 below) |
| Type of submission |
Corrections that do not affect project design
Permanent changes from the monitoring plan or the monitoring methodology
Changes to the project or programme design
|
| Applicable crediting period | 17 Feb 13 - 16 Feb 20 |
| Assessment opinion |
Assessment opinion (368 KB)
|
| Revised PDD |
Revised PDD (1478 KB)
Revised PDD - track changes (1709 KB)
|
| Supplementary documents |
Appendix 1 - BD Calculo ER Providencia I_ver5 31082020 rJCC.xlsx (72 KB)
|
| Signed form |
Signed form (147 KB)
|
| DOE clarification | |
| VVS version | VVS-PA 2.0 |
| Current status | 31 Dec 20 -
Approved
Effective approval date: 31 Dec 20
|
| Historic statuses |
02 Dec 20 -
Request published |

Assessment opinion
Appendix 1 - BD Calculo ER Providencia I_ver5 31082020 rJCC.xlsx