10:18 10 Jan 25
Project:
2848 Bailongjiang Dalijie Hydropower Station
- Request for post-registration changes
Project | 2848 Bailongjiang Dalijie Hydropower Station |
---|---|
PRC ref | PRC-2848-001 |
Process track | Issuance |
DOE | BVI |
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes |
|
Methodology(ies) list | |
Standardized baseline(s) list | |
DOE conducted validation of the changes | When performing a verification for the project activity or PoA stated above (See footnote 1 below) |
Type of submission |
Changes to the project or programme design
|
Applicable crediting period | 06 Dec 09 - 05 Dec 19 |
Assessment opinion | Assessment opinion (145 KB) |
Revised PDD | Revised PDD (534 KB) Revised PDD - track changes (536 KB) |
Supplementary documents | |
Signed form | Signed form (297 KB) |
DOE clarification | |
VVS version | VVS 2.0 |
Current status | 15 Nov 12 -
Approved
Effective approval date: 15 Nov 12
|
Historic statuses |
17 Oct 12 -
Request published |