Project: 5310 Nam Chim Hydro Power Project - Request for post-registration changes
Project 5310 Nam Chim Hydro Power Project
PRC ref PRC-5310-001
Process track Issuance
DOE DTSUS
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
Methodology(ies) list
Standardized baseline(s) list
DOE conducted validation of the changes When performing a verification for the project activity or PoA stated above (See footnote 1 below)
Type of submission Temporary deviations from the monitoring plan or the monitoring methodology
  • Applicable period for proposed deviations (inclusive): 05 Jan 2013 - 15 Jan 2013

Corrections that do not affect project design
  • All changes are in Appendix 1 of the CDM project standard? Yes

Permanent changes from the monitoring plan or the monitoring methodology
  • All changes are in Appendix 1 of the CDM project standard? Yes

Changes to the project or programme design
  • Changes have an impact on: None of the above
Applicable crediting period 01 Jul 12 - 30 Jun 19
Assessment opinion Assessment opinion (114 KB)
Revised PDD Revised PDD (1319 KB)   Revised PDD - track changes (894 KB)
Supplementary documents
Signed form Signed form (439 KB)
DOE clarification
VVS version VVS 2.0
Current status 02 Aug 13 - Approved
Effective approval date: 02 Aug 13
Historic statuses 04 Jul 13 - Request published