Project:
7027 Porto do Delta Wind Power Plant CDM Project
- Request for post-registration changes
Project | 7027 Porto do Delta Wind Power Plant CDM Project |
---|---|
PRC ref | PRC-7027-001 |
Process track | Prior approval |
DOE | RINA |
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes |
No changes |
Methodology(ies) list | |
Standardized baseline(s) list | |
DOE conducted validation of the changes | Prior to commencement of a verification for the project activity or PoA stated above |
Type of submission |
Permanent changes from the monitoring plan or the monitoring methodology
Changes to the project or programme design
Change to the start date of the crediting period
|
Applicable crediting period | 04 Nov 16 - 03 Nov 23 |
Assessment opinion |
![]() |
Revised PDD |
![]() ![]() |
Supplementary documents |
![]() ![]() |
Signed form |
![]() |
DOE clarification |
![]() ![]() ![]() ![]() |
VVS version | VVS-PA 2.0 |
Current status | 25 Jan 21 -
Approved
Effective approval date: 24 Jan 21
|
Historic statuses |
23 Nov 20 -
Published 07 Dec 20 - Awaiting DOE clarifications 21 Dec 20 - DOE clarifications received 21 Dec 20 - Summary note being prepared 04 Jan 21 - Awaiting EB decision |