Project: 3490 Inner Mongolia Yihewusu Phase II 49.5 MW Wind Power Project - Request for post-registration changes
Project 3490 Inner Mongolia Yihewusu Phase II 49.5 MW Wind Power Project
PRC ref PRC-3490-001
Process track Prior approval
DOE BVI
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
Methodology(ies) list
Standardized baseline(s) list
DOE conducted validation of the changes When performing a verification for the project activity or PoA stated above (See footnote 1 below)
Type of submission Corrections that do not affect project design
  • All changes are in Appendix 1 of the CDM project standard? Yes

Permanent changes from the monitoring plan or the monitoring methodology
  • All changes are in Appendix 1 of the CDM project standard? No
Applicable crediting period 25 Nov 10 - 24 Nov 17
Assessment opinion Assessment opinion (474 KB)
Revised PDD Revised PDD (900 KB)   Revised PDD - track changes (965 KB)
Supplementary documents
Signed form Signed form (46 KB)
DOE clarification
VVS version VVS 2.0
Current status 27 Aug 13 - Approved
Effective approval date: 26 Aug 13
Historic statuses 23 Jul 13 - Published
23 Jul 13 - Summary note being prepared
06 Aug 13 - Awaiting EB decision