18:45 18 May 25
Project:
5162 Gansu Heihe Baopinghe Hydropower Project
- Request for post-registration changes
Project | 5162 Gansu Heihe Baopinghe Hydropower Project |
---|---|
PRC ref | PRC-5162-001 |
Process track | Prior approval |
DOE | TÜV NORD |
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes |
|
Methodology(ies) list | |
Standardized baseline(s) list | |
DOE conducted validation of the changes | When performing a verification for the project activity or PoA stated above (See footnote 1 below) |
Type of submission |
Permanent changes from the monitoring plan or the monitoring methodology
|
Applicable crediting period | 24 Jun 12 - 23 Jun 22 |
Assessment opinion |
![]() |
Revised PDD |
![]() ![]() |
Supplementary documents |
![]() ![]() ![]() |
Signed form |
![]() |
DOE clarification | |
VVS version | VVS 2.0 |
Current status | 30 Nov 12 -
Approved
Effective approval date: 28 Nov 12
|
Historic statuses |
08 Oct 12 -
Published 19 Oct 12 - Awaiting DOE clarifications 30 Oct 12 - DOE clarifications received 30 Oct 12 - Summary note being prepared 08 Nov 12 - Awaiting EB decision |