05:16 06 Jan 25
Project:
5640 Dashiqiao Central Heating Project
- Request for post-registration changes
Project | 5640 Dashiqiao Central Heating Project |
---|---|
PRC ref | PRC-5640-001 |
Process track | Prior approval |
DOE | BVI |
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes |
|
Methodology(ies) list | |
Standardized baseline(s) list | |
DOE conducted validation of the changes | When performing a verification for the project activity or PoA stated above (See footnote 1 below) |
Type of submission |
Corrections that do not affect project design
Permanent changes from the monitoring plan or the monitoring methodology
|
Applicable crediting period | 17 May 12 - 16 May 22 |
Assessment opinion | Assessment opinion (290 KB) |
Revised PDD | Revised PDD (670 KB) Revised PDD - track changes (682 KB) |
Supplementary documents |
Appendix 1 - Registered PDD_Dashiqiao_5640 VVM to VVS.pdf (732 KB)
|
Signed form | Signed form (1838 KB) |
DOE clarification | |
VVS version | VVS 2.0 |
Current status | 06 Jan 14 -
Approved
Effective approval date: 16 Dec 13
|
Historic statuses |
01 Oct 13 -
Published 15 Oct 13 - Awaiting DOE clarifications 13 Nov 13 - DOE clarifications received 13 Nov 13 - Summary note being prepared 25 Nov 13 - Awaiting EB decision |
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: