22:25 24 Oct 25
Project:
0772 Waste Heat based 10 MW captive power project “GPIL- WHRB 2” CDM PROJECT ACTIVITY
- Request for post-registration changes
| Project | 0772 Waste Heat based 10 MW captive power project “GPIL- WHRB 2” CDM PROJECT ACTIVITY |
|---|---|
| PRC ref | PRC-0772-002 |
| Process track | Prior approval |
| DOE | KBS |
|
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes |
No changes |
| Methodology(ies) list | |
| Standardized baseline(s) list | |
| DOE conducted validation of the changes | Prior to commencement of a verification for the project activity or PoA stated above |
| Type of submission |
Permanent changes from the monitoring plan or the monitoring methodology
|
| Applicable crediting period | 18 Feb 07 - 17 Feb 17 |
| Assessment opinion |
Assessment opinion (213 KB)
|
| Revised PDD |
Revised PDD (919 KB)
Revised PDD - track changes (970 KB)
|
| Supplementary documents | |
| Signed form |
Signed form (1231 KB)
|
| DOE clarification | |
| VVS version | VVS 7.0 |
| Current status | 03 Mar 15 -
Approved
Effective approval date: 03 Mar 15
|
| Historic statuses |
27 Jan 15 -
Published 27 Jan 15 - Summary note being prepared 10 Feb 15 - Awaiting EB decision |

Assessment opinion
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: