Project: 3791 La Paloma Hydroelectric Power Plant, Chile - Request for post-registration changes
Project 3791 La Paloma Hydroelectric Power Plant, Chile
PRC ref PRC-3791-001
Process track Issuance
DOE TÜV SÜD
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
Methodology(ies) list
Standardized baseline(s) list
DOE conducted validation of the changes When performing a verification for the project activity or PoA stated above (See footnote 1 below)
Type of submission Permanent changes from the monitoring plan or the monitoring methodology
  • All changes are in Appendix 1 of the CDM project standard? Yes
Applicable crediting period 20 Nov 10 - 19 Nov 17
Assessment opinion Assessment opinion (1748 KB)
Revised PDD Revised PDD (4554 KB)   Revised PDD - track changes (4569 KB)
Supplementary documents
Signed form Signed form (166 KB)
DOE clarification
VVS version VVS 2.0
Current status 04 Jul 13 - Approved
Effective approval date: 04 Jul 13
Historic statuses 05 Jun 13 - Request published